Company News
-
TGC-1 continues the Paz Cascade's HPP sweeping rebuild in Murmansk Oblast
On 21 October 2019, a new transformer was delivered to Yanikoski HPP of TGC-1. The replacement of equipment is carried out within the framework of the sweeping rebuild of hydro power plant
-
Vitaly Markelov is elected the Chairman of the Board of Directors of TGC-1
On 15 October 2019, TGC-1's Board of Directors held a meeting in the form of absentee voting
-
New equipment for Verkhne-Tulomskaya HPP of TGC-1 has passed functional testing
On 3 October 2019, functional testing of the impeller for hydroelectric generating unit No. 1 of Verkhne-Tulomskaya HPP was conducted in the Czech Republic at the ČKD Blansko Holding plant, a subsidiary of JSC TYAZHMASH. Representatives of TGC-1 and the general contractor Teploenergoremont LLC took part in the testing. The purpose of the testing is to confirm the main functional characteristics of the new impeller
-
TGC-1 received the award of MediaTEK-2019 All-Russian Contest
On 3 October 2019, the awarding ceremony of the Fifth MediaTEK-2019 All-Russian Contest was held as part of the business programme of the Russian Energy Week International Forum
-
Vadim Vederchik was appointed Managing Director of TGC-1
Vadim Vederchik was appointed Managing Director of TGC-1 in connection with the termination of an employment contract with Alexey Barvinok, the former General Director of TGC-1
-
Shareholders resolved to transfer the powers of TGC-1 sole executive body to Gazprom Energoholding LLC
On 27 September 2019, Extraordinary General Shareholders Meeting of TGC-1 took place as an absent voting
-
TGC-1 power plants in St. Petersburg have switched to winter operating mode
Starting from 24 September 2019, in accordance with the order of the Energy and Engineering Committee under St. Petersburg Administration, nine combined heat and power plants of TGC-1 in St. Petersburg will operate in a winter heat delivery mode. At the same time, the connection of residential facilities, adjustment of domestic heat supply systems is made by management organisations in stages and takes several days
-
S&P Global Ratings approved the rating of TGC-1 as BBB-/Stable
International rating agency S&P Global Ratings approved the rating of TGC-1 as BBB-/Stable.
-
Petrozavodskaya CHPP switched to winter operating mode
On 20 September 2019, Petrozavodskaya CHPP, the major heat supply plant of Petrozavodsk, switched to winter operating mode, in accordance with the order of the Ministry of Construction, Housing and Communal Services, and Energy of the Republic of Karelia