TGC-1 is continuing the setting-up of the sound attenuator at Petrozavodskaya CHP

25 April 2012

TGC-1 is continuing the setting-up of the sound attenuator at Petrozavodskaya CHP which provides heat to more than 85% of the housing stock of the city.

Now the equipment lowering level of sound pressure in areas adjacent to the station works at two of three power-generating boiler. In accordance with the annual repair schedule it is planned to make adjustment of the last sound attenuator on the power-generating boiler No. 2 in the second half of May within the complex refurbishment project.