На объектах ОАО «ТГК-1» продолжается ввод в эксплуатацию систем обмена технологической информацией
At the Apatitskaya CHPP of JSC TGC-1, the system of technological data exchange with the automated system of the system operator was put into trial operation (STDE ASSO). On November 25-27, the similar system will undergo comprehensive test at the Borisoglebskaya HPP of JSC TGC-1.
The STDE ASSO collects and transmits data about the state of the main equipment to the operating and maintenance personnel of the plant and the System Operator.
‘Introduction of STDE ASSO is closing to an end. Before the end of the year, we expect starting the system at all facilities of JSC TGC-1 in Murmansk Oblast. This will allow us to get the operating parameters of the equipment accurately and quickly to control the electricity generation and optimise the load modes,’ - Oleg Tyapin, Deputy Chief Engineer of the Kolskiy Branch of JSC TGC-1 explained.
The introduction of the STDE ASSO at the facilities of the Kolskiy Branch of JSC TGC-1 was started in 2010.