На ГЭС Суури-Йоки ПАО «ТГК-1» завершился капитальный ремонт

6 August 2018 года

An overhaul of the hydroelectric generating unit No. 2 at Suuri Ioki HPP located on the Tulemajoki River in the Western part of Karelia was completed on 3 August 2018 as part of implementation of TGC-1's Repair and Maintenance Programme

An overhaul of the hydroelectric generating unit No. 2 at Suuri Ioki HPP located on the Tulemajoki River in the Western part of Karelia was completed on 3 August 2018 as part of implementation of TGC-1's Repair and Maintenance Programme.

- The repair was performed by experts of the Smaller HPPs Group of the Suna HPPs Cascade, as well as by the personnel of the Cascade. Within four months a great work was done for commissioning and regulation of the hydroelectric generating unit's turbine, the most important parts of the hydroelectric generating unit were repaired, and the electrical part of the equipment was adjusted.- The hydroelectric generating unit at Suuri Yoki HPP was successfully put into operation upon completion of complex testing.

Power engineers of the Smaller HPPs Group have repaired the equipment without involvement of any third parties for the second time already: - last year, an overhaul of Pieni Yoki HPP equipment was performed in a similar way. Specialists of the power plants developed own working documentation.

Reference

The Smaller HPPs Group of the Suna HPPs Cascade -

TGC-1 is the leading producer and supplier of electricity and heat in the North-West of Russia. TGC-1 comprises 53 electric power plants within four constituent entities of the Russian Federation: St. Petersburg, the Republic of Karelia, and Leningrad and Murmansk Oblasts.

Repair and Maintenance Programme of TGC-1 is aimed at providing safe and continuing equipment operation, improving efficient performance of power plants and raising the environmental safety.