Company News

15 August 2018 года

Power engineers of the Suna HPPs Cascade of TGC-1 improve operational reliability of power equipment

Power engineers of the Suna HPPs Cascade completed an overhaul of the transformer with the capacity of 31.5 MVA at Kondopozhskaya HPP

6 August 2018 года

An overhaul completed at Suuri Ioki HPP of TGC-1, which will celebrate its 100th anniversary two years later

An overhaul of the hydroelectric generating unit No. 2 at Suuri Ioki HPP located on the Tulemajoki River in the Western part of Karelia was completed on 3 August 2018 as part of implementation of TGC-1's Repair and Maintenance Programme

6 August 2018 года

TGC-1 1H 2018 IFRS Profit Grew by 36.7%

TGC-1 releases interim unaudited consolidated Financial Statements for the 6 months period, ended 30 June 2018 prepared in accordance with International Financial Reporting Standards (IFRS).

2 August 2018 года

TGC-1 participated in the meeting of the work group of the Russian-Estonian Commission for Protection and Sustainable Use of Transboundary Waters

A meeting of the work group for complex management of water resources of the Joint Russian-Estonian Commission for Protection and Sustainable Use of Transboundary Waters took place in Tallinn (the Republic of Estonia) on 30-31 July 2018

1 August 2018 года

Power engineers clean the banks of the Svir River

Employees of Nizhne-Svirskaya HPP of TGC-1 collected more than 100 kg of rubbish during cleaning days, that took place as part of the All-Russian action Water of Russia.

26 July 2018 года

TGC-1 releases Financial Statements for H1 2018 According to Russian Accounting Standards

TGC-1 releases financial statements for six months of 2018 developed under Russian Accounting Standards.

25 July 2018 года

Full repair of hydroelectric generating unit is completed at Svetogorskaya HPP of TGC-1

The scheduled repair of hydroelectric generating unit No. 1 with a capacity of 30.5 MW was completed at Svetogorskaya HPP of TGC-1

25 July 2018 года

TGC-1 Presents its Performance Highlights for H1 2018

Electricity generation of TGC-1 for six months of 2018, including PJSC Murmanskaya CHPP, comprised 15,902.2 million kWh, which is 9.6% more than in the respective period of 2017.

23 July 2018 года

Power engineers clean the Tuloma River

As part of the All-Russian action Water of Russia, power engineers of the Tuloma and Serebryanskiye HPPs Cascade of TGC-1 are cleaning up the Tuloma River

17 July 2018 года

TGC-1 is Implementing Summer Repair Campaign

In order to prepare to 2018–2019 autumn-winter period, TGC-1 is planning to carry out 17 overhauls and 9 medium repairs of equipment.