15 May 2019

TGC-1 Group Profit for 1Q 2019 Increased by 5.4%

TGC-1 releases audited consolidated Financial Statements for the 3 months period, ended 31 March, 2019 prepared in accordance with International Financial Reporting Standards (IFRS).

14 May 2019

TGC-1 switches to the summer mode in Petrozavodsk and Pryazhinsky and Prionezhsky districts

From 14 May 2019, Petrozavodskaya CHPP of TGC-1 switched to the summer mode in accordance with the order of the Ministry of Construction, Housing and Utilities and the Energy Industry of the Republic of Karelia

13 May 2019

TGC-1 CHPPs in St. Petersburg have switched to the summer mode

On 13 May 2019 from 3 p.m. all heat power plants of TGC-1 have switched to the summer mode in accordance with the order of the Committee on Energy and Engineering Support of St. Petersburg's Administration

30 April 2019

Wastewater treatment scheme upgraded at Pravoberezhnaya CHPP of TGC-1

Local industrial and storm wastewater treatment facilities were put in trial operation at Pravoberezhnaya CHPP of TGC-1. The modern technologies allow to prepare effluents for reuse in the production cycle

30 April 2019

TGC-1 increased RAS net profit by 25.6% in Q1 2019

TGC-1 published its 3 months 2019 financial statements under the Russian Accounting Standards (RAS).

30 April 2019

TGC-1 increased electricity output of CHPPs by 5.0% in Q1 2019

Electricity output of TGC-1, including PJSC Murmanskaya CHPP, for Q1 2019 comprised 8,370.2 million kWh, which is 5.1% lower than for the same period of 2018.

20 April 2019

A new impeller installed at TGC-1's Verkhne-Tulomskaya HPP

On 20 April 2019, a new impeller was installed at hydroelectric generating unit No. 4 of TGC-1's Verkhne-Tulomskaya HPP. Andrey Chibis, Head of Murmansk Oblast, observed as the work progressed

19 April 2019

The full repair of the equipment at the Palieozerskaya HPP of TGC-1 is completed

As part of the Power System Repair and Maintenance Programme of TGC-1, the full repair of hydroelectric generating unit No.1 with a capacity of 12.5 MW was completed within the stated period at the Palieozerskaya HPP, the upper part of the Suna HPPs Cascade

17 April 2019

Employees of the Ladoga HPPs Cascade of TGC-1 took part in a training on liquidation of power grid equipment failures

On 17 April, a joint emergency training of TGC-1, the Leningrad RED branch of AD SO UES, PJSC Lenenergo and JSC RZhD (Russian Railways) was organised to develop steps to be taken by the personnel of these enterprises in order to liquidate malfunctions in power grid equipment

09 April 2019

Energy workers carried out a thorough training at TGC-1's Narvskaya HPP

On 9 April 2019, a thorough training for water flood-related emergency liquidation took place at TGC-1's Narvskaya HPP