Company News

22 September 2020

Fitch Ratings Affirms TGC-1 at BBB with Stable Outlook

On 1 September 2020, Fitch Ratings affirmed the long-term foreign currency and national currency issuer default ratings (IDR) for TGC-1 at BBB with Stable Outlook, with its short-term foreign currency and national currency IDRs affirmed at F3.

03 September 2020

Murmansk Oblast Government, TGC-1, and "Murmanskaya CHPP" JSC Signed an Agreement to Increase Heat Supply Reliability

September 2, 2020, in Murmansk Andrey Chibis, Governor of the Murmansk Oblast, Vadim Vederchik, Managing Director of TGC-1 PJSC, and Stanislav Nazarov, General Director of "Murmanskaya CHPP" JSC, signed a cooperation agreement.

24 August 2020

TGC-1 Ranks First Among Energy Companies on the Industry-Wide Social Efficiency Ranking

AK&M Rating Agency has released the third Social Efficiency Ranking of major Russian corporations for 2019, with TGC-1 ranking first in the Energy sector.

24 August 2020

TGC-1 Completes Overhaul of the Hydroelectric Generating Unit at One of Russia’s Oldest Hydropower Plants

TGC-1 PJSC has completed the scheduled overhaul of 29.5 MW hydroelectric generating unit no. 2 at Lesogorskaya HPP, one of the oldest power plants in Russia, to increase the reliability of the plant’s equipment.

24 August 2020

TGC-1 Completes Overhaul of the Hydroelectric Generating Unit at Niva HPP-3, Russia’s First Underground HPP

TGC-1 PJSC has completed the scheduled overhaul of 29.5 MW hydroelectric generating unit no. 2 at Lesogorskaya HPP, one of the oldest power plants in Russia, to increase the reliability of the plant’s equipment.

05 August 2020

TGC-1 presents its financial statements under IFRS for H1 2020

TGC-1 releases interim abbreviated unaudited consolidated Financial Statements for the 6 months period, ended 30 June 2020 prepared in accordance with International Financial Reporting Standards (IFRS).

06 August 2020

TGC-1 Increased Core Equipment Reliability at Kondopozhskaya HPP

According to the TGC-1 PJSC’s repair and maintenance programme, the overhaul of hydroelectric generating unit No. 1 has been completed at one of the oldest hydroelectric power plants in Russia and the firstborn of electrification in Karelia: the Kondopozhskaya HPP.

04 August 2020

TGC-1 Has Completed the Overhaul of Equipment on the Most Powerful CHPP in St. Petersburg: Yuznhaya

Power engineers of TGC-1 PJSC have completed the overhaul of the gas turbine, the generator, and the waste heat recovery boiler at Yuzhnaya CHPP. The equipment has been connected to the grid for comprehensive tests under load.

03 August 2020

TGC-1 Began Renovation of the Largest CHPP in the South-West of St. Petersburg

TGC-1 has started the implementation of a project to reconstruct the Avtovskaya CHPP, the largest generation facility in the southwestern part of St. Petersburg.

28 July 2020

TGC-1 presents its performance highlights for H1 2020

Electricity output of TGC-1, including JSC Murmanskaya CHPP, for 6 month 2020 comprised 15,037.6 million kWh, which is 0.3% lower than for the same period of 2019.