Company News

31 August 2018

An overhaul of the boiler unit completed at Vasileostrovskaya CHPP of TGC-1

Power engineers repaired the superheater of the boiler unit No. 8, the drum with separational arrangements, regenerative-type air heaters and other elements of the equipment

21 August 2018

New equipment for Verkhne-Tulomskaya HPP of TGC-1 accepted

The commission comprised of TGC-1, General Contractor Teploenergoremont LLC, and equipment producer JSC TYAZHMASH performed acceptance of the impeller for the hydroelectric generating unit No. 4 of Verkhne-Tulomskaya HPP of TGC-1 in the Czech Republic, at the plant of ČKD Blansko Holding being a subsidiary of JSC TYAZHMASH, as part of the power plant upgrade project

15 August 2018

Power engineers of the Suna HPPs Cascade of TGC-1 improve operational reliability of power equipment

Power engineers of the Suna HPPs Cascade completed an overhaul of the transformer with the capacity of 31.5 MVA at Kondopozhskaya HPP

06 August 2018

An overhaul completed at Suuri Ioki HPP of TGC-1, which will celebrate its 100th anniversary two years later

An overhaul of the hydroelectric generating unit No. 2 at Suuri Ioki HPP located on the Tulemajoki River in the Western part of Karelia was completed on 3 August 2018 as part of implementation of TGC-1's Repair and Maintenance Programme

06 August 2018

TGC-1 1H 2018 IFRS Profit Grew by 36.7%

TGC-1 releases interim unaudited consolidated Financial Statements for the 6 months period, ended 30 June 2018 prepared in accordance with International Financial Reporting Standards (IFRS).

02 August 2018

TGC-1 participated in the meeting of the work group of the Russian-Estonian Commission for Protection and Sustainable Use of Transboundary Waters

A meeting of the work group for complex management of water resources of the Joint Russian-Estonian Commission for Protection and Sustainable Use of Transboundary Waters took place in Tallinn (the Republic of Estonia) on 30-31 July 2018

01 August 2018

Power engineers clean the banks of the Svir River

Employees of Nizhne-Svirskaya HPP of TGC-1 collected more than 100 kg of rubbish during cleaning days, that took place as part of the All-Russian action Water of Russia.